Coke Storage and Handling Project

Whiting Refinery, Whiting, Ind.

Client / Owner
Kinder Morgan Bulk Terminals
Core Market
Process

Project Scope

Graycor Industrial performed civil/mechanical and structural construction for the Coker Material Terminal located at BP’s facility in Whiting, Indiana. Project consisted of two phases: Foundations and underground utilities, and structural, conveyors and piping.

Graycor self-performed the concrete, structural steel, piping, millwright, equipment setting and commissioning work.

Foundations and Underground Utilities:

  • 182 auger cast-in-place piles:

  • 5,200yd3 of poured foundations/pile caps/access ramps

  • 3,350 feet of underground piping    

  • 7,600yd2 of Asphalt paving

  • 4,400 linear feet of rail

  • New MCC room, duct banks and grounding

    Structural, Conveyors and Piping:

  • 400 tons of structural steel (towers)       

  • 2,331 feet of 54” conveyors (10 total)

  • 11,500 feet of service piping      

  • Pump skids / equipment setting              

  • Heat tracing and insulation

  • Commissioning assistance